(a) Generally. In addition to plans, specifications and calculations required elsewhere in the building code, an application for a building permit shall be accompanied by the following:

Method

Required information to on building plans

I

Plans shall clearly indicate construction as specified in sec. 22-429

II

OITL calculations in accordance with sec. 22-430 shall be submitted with the building plans, and shall be certified and stamped by an acoustical engineer, licensed as a professional engineer in the State of Colorado, whom is also a practicing acoustical engineer.

III

Field test report showing the OITL was measured in accordance with ASTM E 966 (current revision at time of plans submittal) and calculated in accordance with ASTM E 1332 (current revision at time of plans submittal) shall be certified and stamped by an acoustical engineer, licensed as a professional engineer in the State of Colorado, whom is also a practicing acoustical engineer.

(b) Details. Plans and specifications shall show in sufficient detail any pertinent data and features of the building and the sound insulation techniques to clearly indicate compliance with the requirements of this article. For pre-fabricated assemblies, such as windows, pre-hung doors, fireplaces, submittals and labeling on the assemblies shall clearly indicate the STC rating of the assembly, and that the testing was performed in accordance with ASTM E 90 (current revision at time of plans submittal) or ASTM E 966 (current revision at time of plans submittal). (Ord. No. 2011-07, § 7, 4-11-2011)